Office Refurbishment, The Hub, Rutherglen Shopping Centre, Glasgow

Refurbishment Washrooms

Client: I10 Design

Location: The Hub, Rutherglen Shopping Centre, Glasgow


Refurbishment involving strip out of all ceilings, walls, doors and floor coverings. All electrics and heating pipes to be stripped out and replaced.

New Ceiling Installation

New 1-hour fire-rated MF ceiling, forming perimeter bulkhead and encasing all supporting beams. All ceilings were taped and filled, with all perimeter walls newly plastered. Walls within the toilets were tiled to 1500mm from floor level with a 200 x 200 ceramic tile.

Electrics Upgrade

Electrical containment was 50mm exposed tray on the ceiling for lighting and smoke detectors, with 100 x 50 galvanised trunking on the walls to accommodate sockets and data. Main office lighting consisted of 1200 x 40 mm LED lights hung from suspension wires from the plasterboard ceiling. Reception, toilet and tea prep had circular recessed LED lights. All electrics are supplied from a newly fitted distribution board.

New Central Heating installation

Heating pipework was hidden in the loft space then dropped into the office area in copper piping, clipped and left exposed. Pipework was then painted out the same colour as the radiator. All heating supplied from a newly fitted gas boiler.

Washroom Improvements

In addition to new ceramic tiling within the toilets, newly fitted cubicles, vanity units and sanitary ware was fitted to within both male and female toilets.

Within the office, new doors were fitted to both toilets, with FD60 doors fitted to the electrical cupboard and boiler cupboard. Office entrance door comprised of FD60 door with central oversized vision panel and glazed over panel.

New Office Tea Prep Area

The tea prep area consisted of new base and wall units, sink and fridge. Ceramic tiled splash back, which the tiles match the ones from the toilets.

Decoration and Flooring

The office was decorated throughout with primarily white walls with some orange/purple feature walls on 4 elevations. Woodwork was decorated light and dark grey. Newly fitted floor coverings were laid throughout, with carpet tiles in the main area and vinyl floor covering to toilet and tea prep. Stairs had a vinyl floor finish with new double stair nosing.

Entrance Signage and Security

The main entrance from the street had a new protruding sign installed with down lights and halo lit unit number. A new key operated, motorised roller shutter was installed as well as a new steel entrance door with mag locks and video intercom.

Related Case Studies

Refurbishment

George House Glasgow Boasts Bright, Modern Interiors

Glazed Partitions Refurbishment Suspended Ceiling

Modern Office Refurbishment for Gist Offices, Cumbernauld

Get in touch

Discuss Your Project

If you have a project in mind you would like to discuss with us, our expert team is always available to discuss it with you and book an appointment to chat in detail. Please dont hesitate to get in touch with us

Contact Us

Our Accreditations

Subscribe to our Newsletter

Subscribe to our monthly Newsletter to receive our latest News and Updates.

Sign up
Contact Us

Get a quote

We will be happy to assist you with any questions

333 Drakemire Drive, Glasgow, Scotland, G45 9SS

Name(Required)
Email(Required)